(970) 224-1991 jack@templeconstructionllc.com Mon. - Fri. 7AM - 5PM

Portfolio

BNN/Tallgrass

Installed a 37 mile 22” SDR 13.5 HDPE pipeline from the North Sterling Reservoir to the New Raymer area. This project was remote, done in a non-lineal fashion due to ROW/landowner complications and was still completed in under 3 months. Multiple long 22” directional bores were completed successfully on this project. Longest bore was 1,600’

Categories